Alinda Villas Construction Update Plot 3
FOUNDATION FOOTING PROCESS 100%
STRUCTURE PROCESS 95%
– GROUND BEAM AND FLOOR STRUCTURE PROCESS 95%
– POOL AND SURGE TANK STRUCTURE PROCESS 95%
– COLUMN 95%
– ROOF BEAM AND ROOF SLAB 95%
ARCHITECTURAL PROCESS 65 %
– BRICK WORK 92 %
ARCHITECTURAL PROCESS 65 %
– PIPE LINE INSTALLATION 75 %
ARCHITECTURAL PROCESS 65 %
– PLASTERING WORK 75 %
ARCHITECTURAL PROCESS 65 %
– FINISHING & MATERIAL INSTALLATION WORK 40 %
ARCHITECTURAL PROCESS 65 %
– PAINTING WORK 45 %
STATUS SUMMARY
FOUNDATION FOOTING PROCESS 100 %
STRUCTURE PROCESS 95 %
– GROUND BEAM AND FLOOR STRUCTURE PROCESS 95%
– POOL AND SURGE TANK STRUCTURE PROCESS 95%
– COLUMN 95%
– ROOF BEAM AND ROOF SLAB 95%
ARCHITECTURAL PROCESS 65 %
– BRICK WORK 92%
– PIPE LINE INSTALLATION 75%
– PLASTERING WORK 75%
– FINISHING & MATERIAL INSTALLATION WORK 40%
– PAINTING WORK 45%
DECORATIVE WORK AND TRANSFER PROCESS 0 %