Alinda Villas Construction Update Plot 4
FOUNDATION FOOTING PROCESS 100 %
STRUCTURE PROCESS 95 %
– GROUND BEAM AND FLOOR STRUCTURE PROCESS 95 %
– POOL AND SURGE TANK STRUCTURE PROCESS 95 %
– COLUMN 95 %
– ROOF BEAM AND ROOF SLAB 95 %
ARCHITECTURAL PROCESS 78 %
– BRICK WORK 95 %
ARCHITECTURAL PROCESS 78 %
– PIPE LINE INSTALLATION 90 %
ARCHITECTURAL PROCESS 78 %
– PLASTERING WORK 90%
ARCHITECTURAL PROCESS 78 %
– FINISHING & MATERIAL INSTALLATION WORK 55 %
ARCHITECTURAL PROCESS 78 %
– PAINTING WORK 60 %
STATUS SUMMARY
FOUNDATION FOOTING PROCESS 100 %
STRUCTURE PROCESS 95 %
– GROUND BEAM AND FLOOR STRUCTURE PROCESS 95%
– POOL AND SURGE TANK STRUCTURE PROCESS 95%
– COLUMN 95%
– ROOF BEAM AND ROOF SLAB 95%
ARCHITECTURAL PROCESS 78 %
– BRICK WORK 95%
– PIPE LINE INSTALLATION 90%
– PLASTERING WORK 90%
– FINISHING & MATERIAL INSTALLATION WORK 55%
– PAINTING WORK 60%
DECORATIVE WORK AND TRANSFER PROCESS 0 %